On March 7, the U.S. District Court for the District of Columbia issued a ruling denying a motion for a preliminary
Dakota Access originally requested an easement in October 2014, and submitted its application to the Corps of Engineers in June 2015. The Corps of Engineers granted an easement to the pipeline pursuant to its authority under the Rivers and Harbors Act in July 2015, and then the present litigation commenced in the District Court. No RFRA claim was made by the tribes at that time. Then, in December 2016, the former Chief of the Corps of Engineers took action to delay any grant of an easement to cross Lake Oahe pending the completion of a robust environmental review, but this directive was terminated once the new administration took office.
On February 8, 2017, the Corps of Engineers notified Congress of its intent to issue the easement, and the next day the Cheyenne River Sioux Tribe filed its motion for preliminary injunction. The court determined that “because of the Plaintiff’s delay in raising this religious-exercise objection and the negative impact of that delay on the Corps and Dakota Access, the court concludes that the requested preliminary-injunctive relief is barred by laches.” In addition, the District Court found that the tribes were unlikely to establish that the “grant of this easement imposes a substantial burden on its religious exercise such that it will succeed on the merits of its RFRA claim.”
Photo: Karl-Ludwig Poggemann, “Signing orders to move forward with the construction of the Keystone XL and Dakota Access pipelines in the Oval Office” – Creative Commons